Nikhil Builders
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+25 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Saloni EnclaveP51800007822 | Kurla | 2017 | Certificate Signed | 18 Sep 2018 | 30 Oct 2020 | +25 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 25 months, for Saloni Enclave (P51800007822).
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus M/s Nikhil Builders (Suo Motu Case No. 38 of 2019) dated 17th December 2019 · Saloni Enclave · P51800007822 · 17 Dec 2019
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology