Nidhaan Buildcon Private Limited
Company or firm · 2 projects · 3 MahaRERA registrations
Also appears as M/S. NIDHAAN BUILDCON PRIVATE LIMITED
2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Nidhaan CloverP51800010930 | Kurla | 2017 | Certificate Signed | 1 Jan 2022 | 1 Jan 2022 | On date |
| Nidhaan CineplazaP51800014315 | Kurla | 2017 | Certificate Signed | 30 Sep 2018 | 30 Sep 2019 | +12 months |
| Nidhaan CloverP51800019932 | Kurla | 2019 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Nidhaan Cineplaza (P51800014315).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology