0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nidhaan CloverP51800010930Kurla2017Certificate Signed1 Jan 20221 Jan 2022On date
Nidhaan CineplazaP51800014315Kurla2017Certificate Signed30 Sep 201830 Sep 2019+12 months
Nidhaan CloverP51800019932Kurla2019Certificate Signed30 Jun 202430 Jun 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nidhaan CloverOn date
  • Nidhaan Cineplaza+12 mo
  • Nidhaan CloverOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Nidhaan Cineplaza (P51800014315).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.