Neumec And Sangam Jv
Company or firm · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+30 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shahid NagarP51900002527 | Mumbai City | 2017 | Not reported | 31 Dec 2027 | — | On date |
| Composite Building No2P51900018301 | Mumbai City | 2018 | Not reported | 30 Jun 2022 | 30 Jun 2027 | +60 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 60 months, for Composite Building No2 (P51900018301).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: SHAHID NAGAR (Regulatory Case No. 417 OF 2025) dated 14 Nov, 2025. · Shahid Nagar · P51900002527 · 14 Nov 2025
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology