Nerkar Properties Llp
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 4 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ganesh GunjanP51600006346 | Nashik (M Corp.) | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Ganesh AvenueP51600007654 | Nashik (M Corp.) | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Ganesh SparshP51600008749 | Nashik (M Corp.) | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| The CrownP51600029107 | Nashik | 2021 | Not reported | 30 Jun 2023 | 31 May 2024 | +11 months |
| Ganesh AarambhP51600047860 | Nashik (M Corp.) | 2022 | Not reported | 28 Feb 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Ganesh Gunjan (P51600006346).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology