Neev Infrastructure Pvt. Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as Neev Infrastructure Pvt Ltd · Neev Infrastructure Pvt. Ltd.

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+41 movs RERA proposed date · 1 extended
Regulatory cases2MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Neev AmberwoodP51800002969Andheri2017Not reported31 Mar 2019—On date
Neev GalaxyP51800003057Borivali2017Not reported31 Dec 201830 Sep 2025+81 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Neev AmberwoodOn date
  • Neev Galaxy+81 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 81 months, for Neev Galaxy (P51800003057).
  • MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology