Skip to content
Deedo home
Menu

Navnath Infrastructures Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Navnath JayasP51800051536Pahadi-Goregaon2023Not reported31 Dec 2027—On date
Navnath NandikeshP51800078399Pahadigoregaon2024Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Navnath JayasOn date
  • Navnath NandikeshOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology