Navkar Infra Projects

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
20%Kept RERA date1 of 5 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sakshat NavkarP51800000503Borivali2017Certificate Signed30 Sep 201931 May 2025+68 months
Yellow RosesP51800000712Borivali2017Certificate Signed20 Jul 201931 Dec 2024+65 months
Navkar ParadiseP51800000715Borivali2017Certificate Signed15 Jun 202115 Dec 2022+18 months
Shanti VijayP51800000790Borivali2017Certificate Signed10 Jul 201910 Jul 2019On date
Sajag ChsP51800001223Borivali2017Certificate Signed24 Jun 201923 Dec 2020+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sakshat Navkar+68 mo
  • Yellow Roses+65 mo
  • Navkar Paradise+18 mo
  • Shanti VijayOn date
  • Sajag Chs+18 mo

Track record notes

  • 1 of 5 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 68 months, for Sakshat Navkar (P51800000503).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology