Navkar Groups Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 2 extended
3Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Navkar HeightsP51800004596Borivali2017Certificate Signed30 Dec 202131 Dec 2023+24 months
Navkar Girija SadanP51800006112Borivali2017Certificate Signed31 Dec 201831 Dec 2027+108 months
Navkar MannatP52800022020Zadgaon Ct2019Certificate Signed30 Dec 202230 Dec 2022On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Navkar Heights+24 mo
  • Navkar Girija Sadan+108 mo
  • Navkar MannatOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 108 months, for Navkar Girija Sadan (P51800006112).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology