Navkar Developers

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Tulsi Centre PointP52000000571Neral2017Certificate Signed31 Dec 201930 Dec 2021+24 months
Tulsi Centre PointP52000049922Neral2023Certificate Signed31 Jul 202431 Jul 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Tulsi Centre Point+24 mo
  • Tulsi Centre PointOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Tulsi Centre Point (P52000000571).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.