Nav Durga Construction Company

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Saraswati Chsl Plot 8 AP51800001302Kurla2017Certificate Signed31 Dec 201831 Dec 2018On date
Jai Gopi Krishna ChslP51800006482Kurla2017Certificate Signed31 Dec 201730 Apr 2018+4 months
Shree Saraswati Chs Ltd Plot 8bP51800017436Kurla2018Certificate Signed30 Nov 202630 Nov 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Saraswati Chsl Plot 8 AOn date
  • Jai Gopi Krishna Chsl+4 mo
  • Shree Saraswati Chs Ltd Plot 8bOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Jai Gopi Krishna Chsl (P51800006482).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology