National Happy Homes

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Jade VedantP51900001373Mumbai City2017Certificate Signed31 Mar 201931 Mar 2019On date
Kamal KunjP51900002602Mumbai City2017Certificate Signed30 Sep 201930 Sep 2019On date
Jade ImperialP51900007860Mumbai City2017Certificate Signed30 Mar 202330 Mar 2023On date
Jade CrestP51900033760Mumbai City2022Certificate Signed30 Sep 202630 Sep 2026On date
Jade SolitaireP51900051442Ward Fnorth2023Certificate Signed31 Mar 202731 Jul 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Jade VedantOn date
  • Kamal KunjOn date
  • Jade ImperialOn date
  • Jade CrestOn date
  • Jade Solitaire+4 mo

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Jade Solitaire (P51900051442).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology