Nashik Housing & Area Development Board, Nashik

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Emerald EstatePM1220002500512Satpur2025Certificate Signed30 Sep 203030 Jan 2031+4 months
Primrose PlazaPR1220002500862Nashik (M Corp.)2025Certificate Signed31 May 203030 Sep 2030+4 months
Orchid OasisPR1220002500891Nashik (M Corp.)2025Certificate Signed30 Sep 203030 Jan 2031+4 months
Harmony HeavenPR1220002500966Nashik (M Corp.)2025Certificate Signed30 Nov 203030 Mar 2031+4 months
Camelia ComplexPM1220002501462Nashik (M Corp.)2025Certificate Signed1 Jan 20321 May 2032+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Emerald Estate+4 mo
  • Primrose Plaza+4 mo
  • Orchid Oasis+4 mo
  • Harmony Heaven+4 mo
  • Camelia Complex+4 mo

Track record notes

  • Longest extension on record: 4 months, for Emerald Estate (PM1220002500512).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology