Nashik Housing & Area Development Board, Nashik
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Emerald EstatePM1220002500512 | Satpur | 2025 | Certificate Signed | 30 Sep 2030 | 30 Jan 2031 | +4 months |
| Primrose PlazaPR1220002500862 | Nashik (M Corp.) | 2025 | Certificate Signed | 31 May 2030 | 30 Sep 2030 | +4 months |
| Orchid OasisPR1220002500891 | Nashik (M Corp.) | 2025 | Certificate Signed | 30 Sep 2030 | 30 Jan 2031 | +4 months |
| Harmony HeavenPR1220002500966 | Nashik (M Corp.) | 2025 | Certificate Signed | 30 Nov 2030 | 30 Mar 2031 | +4 months |
| Camelia ComplexPM1220002501462 | Nashik (M Corp.) | 2025 | Certificate Signed | 1 Jan 2032 | 1 May 2032 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Emerald Estate (PM1220002500512).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology