Individual promoter · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Janki SahaniwasP50500023065Nagpur (M Corp.)2019Not reported30 Sep 2024—On date
Tulsi SahaniwasP50500051527Nagpur (M Corp.)2023Not reported31 Mar 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Janki SahaniwasOn date
  • Tulsi SahaniwasOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.