Namrata Developers Pvt. Ltd
Company or firm · 5 projects · 5 MahaRERA registrations
Also appears as NAMRATA DEVELOPERS PRIVATE LIMITED
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Namrata Eco City 2.0P52100000227 | Talegaon Dabhade (R) | 2017 | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | On date |
| Weekender Birds ViewP52100001626 | Talegaon Dabhade (M Cl) | 2017 | Certificate Signed | 30 May 2018 | 30 May 2018 | On date |
| Eco ShoppyP52100015225 | Talegaon Dabhade (R) | 2018 | Certificate Signed | 1 Apr 2021 | 1 Apr 2021 | On date |
| Happycity VaraleP52100018045 | Talegaon Dabhade (R) | 2018 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Happycity VaraleP52100078221 | Varale | 2024 | Certificate Signed | 30 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Happycity Varale (P52100078221).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: HAPPYCITY VARALE (Regulatory Case No. 292 OF 2024) dated 20 Jan, 2025. · Happycity Varale · P52100018045 · 20 Jan 2025
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology