Naiknavare Housing Development Pvt.Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Avasa WoodlandP52100054049Mahalunge2023Not reported30 Dec 2025—On date
Avasa ParklandP52100054938Mahalunge2024Not reported31 Dec 202430 Dec 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Avasa WoodlandOn date
  • Avasa Parkland+12 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Avasa Parkland (P52100054938).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology