Nagarkar Developers
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+15 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Natures Blessings phase IP52100006429 | Gorhe Bk. | 2017 | Certificate Signed | 30 Sep 2019 | 30 Mar 2022 | +30 months |
| Natures Blessings Phase IIP52100019933 | Pune (M Corp.) | 2019 | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 30 months, for Natures Blessings phase I (P52100006429).
Regulatory cases across projects
- DeregisteredDeregistered: Natures Blessings Phase Ii · Natures Blessings Phase II · P52100019933
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology