Nabar Associates

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
ShivankP52100009452Pune (M Corp.)2017Not reported31 Dec 201731 Dec 2018+12 months
Shankar HeightsP52100020727Haveli2019Not reported30 Apr 2023—On date
PannaP52100045604Kothrud2022Not reported30 Jun 2026—On date
Opulence TowersP52100052161Pashan2023Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shivank+12 mo
  • Shankar HeightsOn date
  • PannaOn date
  • Opulence TowersOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Shivank (P52100009452).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology