N B Bhondve Builders

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Bhalchandra Vihar Phase-III/M1,m2P52100046946Ravet2022Not reported30 Jun 202429 Jun 2025+12 months
Bhalchandra Vihar Phase - IV/M3P52100047005Ravet2022Not reported30 Jun 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Bhalchandra Vihar Phase-III/M1,m2+12 mo
  • Bhalchandra Vihar Phase - IV/M3On date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Bhalchandra Vihar Phase-III/M1,m2 (P52100046946).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology