Mumbai Shelter Housing Development Pvt Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+42 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nehru Nagar Mangal Prabhat Chs Ltd Building No-9P51800008871Kurla2017Not reported31 Jul 201930 Jan 2023+42 months
Siddharth Nagar Abhiman Chs Ltd Building No-25P51800010246Borivali2017Not reported31 Dec 201930 Jun 2023+42 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nehru Nagar Mangal Prabhat Chs Ltd Building No-9+42 mo
  • Siddharth Nagar Abhiman Chs Ltd Building No-25+42 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Nehru Nagar Mangal Prabhat Chs Ltd Building No-9 (P51800008871).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology