Multi Space Developers Private Limited
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Praneeta HeightsP51800055133 | Borivali | 2024 | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Gaurav GalaxyP51800076694 | Gorai | 2024 | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 months |
| Skylark HeightsP51800080704 | Gorai | 2025 | Certificate Signed | 11 Feb 2029 | 11 Jun 2029 | +4 months |
| Ashwamedh HeightsPM1180002501982 | Borivali | 2026 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Gaurav Galaxy (P51800076694).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology