Mukesh Nilkhantrao Jadhav

Individual promoter · 6 projects · 6 MahaRERA registrations

6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
83%Kept RERA date5 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Yash ApartmentP52400019233Khadgaon2019Certificate Signed31 Dec 201931 Dec 2019On date
Sai Madhusindhu ApartmentP52400021889Latur (M Cl)2019Certificate Signed30 Nov 202030 Nov 2020On date
Sai Gulab ComlpexP52400028568Latur (M Cl)2021Certificate Signed30 Sep 202230 Sep 2022On date
Sai Mathura ApartmentP52400031907Latur (M Cl)2021Certificate Signed30 Dec 202230 Dec 2022On date
Sai Suman ViharP52400050256Latur (M Cl)2023Certificate Signed31 Mar 202431 Mar 2024On date
P S Patil Residential BuildingP52400080633Latur (M Cl)2025Certificate Signed30 May 202630 Sep 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Yash ApartmentOn date
  • Sai Madhusindhu ApartmentOn date
  • Sai Gulab ComlpexOn date
  • Sai Mathura ApartmentOn date
  • Sai Suman ViharOn date
  • P S Patil Residential Building+4 mo

Track record notes

  • 5 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for P S Patil Residential Building (P52400080633).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology