Mukesh Nilkhantrao Jadhav
Individual promoter · 6 projects · 6 MahaRERA registrations
6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
83%Kept RERA date5 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai Yash ApartmentP52400019233 | Khadgaon | 2019 | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Sai Madhusindhu ApartmentP52400021889 | Latur (M Cl) | 2019 | Certificate Signed | 30 Nov 2020 | 30 Nov 2020 | On date |
| Sai Gulab ComlpexP52400028568 | Latur (M Cl) | 2021 | Certificate Signed | 30 Sep 2022 | 30 Sep 2022 | On date |
| Sai Mathura ApartmentP52400031907 | Latur (M Cl) | 2021 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Sai Suman ViharP52400050256 | Latur (M Cl) | 2023 | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| P S Patil Residential BuildingP52400080633 | Latur (M Cl) | 2025 | Certificate Signed | 30 May 2026 | 30 Sep 2026 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for P S Patil Residential Building (P52400080633).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology