Individual promoter · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Ganesh HillviewP52100005537Haveli2017Certificate Signed30 Dec 201830 Dec 2018On date
Shree Ganesh HilllviewP52100020633Charholi2019Certificate Signed30 Dec 20228 Feb 2023+2 months
Shree Ganesh Hill View Wing CP52100050230Charholi2023Certificate Signed31 Dec 202431 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Ganesh HillviewOn date
  • Shree Ganesh Hilllview+2 mo
  • Shree Ganesh Hill View Wing COn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 2 months, for Shree Ganesh Hilllview (P52100020633).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.