Model Developers And Builders
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| AmrutwelP52700001718 | Satara | 2017 | Not reported | 26 Oct 2019 | — | On date |
| Samruddhi NiwasP52700004270 | Satara | 2017 | Not reported | 2 Nov 2020 | — | On date |
| Swami PraasadP52700021482 | Satara | 2019 | Certificate Signed | 28 Nov 2022 | 28 Nov 2022 | On date |
| Siddhivinayak PlazaP52700025198 | Satara | 2020 | Not reported | 18 Dec 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology