Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sun City - Ambegaon Phase-IP52100026141Ambegaon Bk2020Certificate Signed30 Sep 202530 Sep 2025On date
Sun City AmbegaonP52100030334Ambegaon Bk2021Certificate Signed31 Mar 202531 Mar 2025On date
Sun City AmbegaonP52100051600Ambegaon Bk2023Certificate Signed31 Mar 202631 Mar 2026On date
Sun OrchidP52100055156Kothrud2024Certificate Signed30 Jun 202730 Oct 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sun City - Ambegaon Phase-IOn date
  • Sun City AmbegaonOn date
  • Sun City AmbegaonOn date
  • Sun Orchid+4 mo

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Sun Orchid (P52100055156).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology