Mitra Reality
Company or firm · 3 projects · 3 MahaRERA registrations
Also appears as M/S MITRA REALITY
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai PearlP51700030340 | Badlapur (M Cl) | 2021 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Sai FloraP51700048154 | Badlapur (M Cl) | 2022 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Sai Girnar Chs LtdP51700079744 | Badlapur (M Cl) | 2025 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Sai Flora (P51700048154).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology