Mitra Reality

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as M/S MITRA REALITY

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai PearlP51700030340Badlapur (M Cl)2021Certificate Signed31 Dec 202531 Dec 2025On date
Sai FloraP51700048154Badlapur (M Cl)2022Certificate Signed31 Dec 202630 Apr 2027+4 months
Sai Girnar Chs LtdP51700079744Badlapur (M Cl)2025Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai PearlOn date
  • Sai Flora+4 mo
  • Sai Girnar Chs Ltd+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Sai Flora (P51700048154).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology