Mishal Construction Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gulistan Manzil Co-operative Housing Society LimitedP51900003234Kurla2017Certificate Signed30 Jun 201830 Jun 2019+12 months
Pant Nagar Ganadhiraj CHSLP51900007103Kurla2017Certificate Signed31 Dec 202731 Dec 2027On date
Shri Krishin Co-operative Housing Society LimitedP51900009332Kurla2017Certificate Signed30 Jun 201930 Dec 2022+42 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gulistan Manzil Co-operative Housing Society Limited+12 mo
  • Pant Nagar Ganadhiraj CHSLOn date
  • Shri Krishin Co-operative Housing Society Limited+42 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Shri Krishin Co-operative Housing Society Limited (P51900009332).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.