Millennia Schemes Private Limited
Company or firm · 1 project · 1 MahaRERA registration
Also appears as Goel Ganga India Pvt Ltd
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ganga Millennia Undri Building J,k,l,m And NP52100025883 | Undri | 2020 | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: GANGA MILLENNIA UNDRI BUILDING J, K, L, M AND N (Regulatory Case No. 314 OF 2024) dated 26 Dec 2024. · Ganga Millennia Undri Building J,k,l,m And N · P52100025883 · 26 Dec 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology