Milind Govind Bartakke

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
ChandranilP52700024989Godoli (Ct)2020Not reported28 Feb 2026—On date
Bramhachaitanya HeightsP52700050673Khed (Ct)2023Not reported26 Feb 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • ChandranilOn date
  • Bramhachaitanya HeightsOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology