Mhada
Company or firm · 16 projects · 16 MahaRERA registrations
16Projects16 RERA registrations
0Completedas reported on MahaRERA project pages
53%Kept RERA date8 of 15 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 8 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Construction of 406 TR TS 442 EWS 258 MIG TS at Gavanpada Mulund east MumbaiP51800000024 | Kurla | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| R-4 mankhurdP51800000034 | Kurla | 2017 | Certificate Signed | 22 Aug 2018 | 31 Jul 2019 | +11 months |
| Pratiksha Nagar Phase IVP51900000050 | Ward Fnorth | 2017 | Certificate Signed | 31 Dec 2017 | 30 Oct 2020 | +34 months |
| Tungwa PowaiP51800000056 | Andheri | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2019 | +12 months |
| Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli eastP51800000058 | Kurla | 2017 | Certificate Signed | 30 Dec 2022 | 31 Mar 2026 | +39 months |
| Bombay Dyeing MillP51900004280 | Ward Fnorth | 2017 | Certificate Signed | 31 Dec 2022 | 30 Dec 2023 | +12 months |
| Pratiksha Nagar Sion Phase VP51900004885 | Ward Fnorth | 2017 | Certificate Signed | 31 Dec 2026 | 30 Jun 2027 | +6 months |
| Construction of Mill Workers Tenements at Shrinivas MIll Lower ParelP51900007421 | Ward Gsouth | 2017 | Certificate Signed | 31 Dec 2022 | 30 Dec 2023 | +12 months |
| Construction of Transit and EWS tenements at Antop Hill WadalaP51900012109 | Ward Fnorth | 2017 | Certificate Signed | 31 Jul 2023 | 31 Jul 2023 | On date |
| Jubilee MillP51900000021 | Ward Fsouth | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Century MillP51900000022 | Ward Gsouth | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Western India MillP51900000025 | Ward Fsouth | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Prakash Cotton MillP51900000028 | Ward Gsouth | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Bharat MillP51900000032 | Ward Gsouth | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Ruby MillP51900000043 | Ward Gnorth | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Construction of MIG t/s on open plot on land bearing S.No.01 pt. on CTS No. 1/3 village kopari powaiP51800077430 | Kopari | 2024 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
Show all 16 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 16 registrations
Track record notes
- 8 of 15 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 39 months, for Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east (P51800000058).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology