Mgm Associates
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| 64 Meridien Phase IP52100024750 | Haveli | 2020 | Certificate Signed | 30 Oct 2024 | 30 Oct 2024 | On date |
| 64 Meridien Phase IIP52100049864 | Ravet | 2023 | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| 64 Meridien Tower EP52100052721 | Ravet | 2023 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for 64 Meridien Tower E (P52100052721).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
