Mercury Artharaj Landmarks Aop
Company or firm · 2 projects · 4 MahaRERA registrations
2Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Gulmohar ParkP52100007126 | Dehu | 2017 | Certificate Signed | 30 Dec 2019 | 30 Dec 2019 | On date |
| Royal CassiaP52100019483 | Dehu | 2019 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Gulmohar ParkP52100023073 | Dehu | 2019 | Certificate Signed | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| Royal CassiaP52100026939 | Dehu | 2020 | Certificate Signed | 28 Feb 2025 | 31 Jul 2027 | +29 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 29 months, for Royal Cassia (P52100026939).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology