Mercury Artharaj Landmarks Aop

Company or firm · 2 projects · 4 MahaRERA registrations

2Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gulmohar ParkP52100007126Dehu2017Certificate Signed30 Dec 201930 Dec 2019On date
Royal CassiaP52100019483Dehu2019Certificate Signed30 Dec 202330 Dec 2023On date
Gulmohar ParkP52100023073Dehu2019Certificate Signed30 Dec 202329 Dec 2024+12 months
Royal CassiaP52100026939Dehu2020Certificate Signed28 Feb 202531 Jul 2027+29 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gulmohar ParkOn date
  • Royal CassiaOn date
  • Gulmohar Park+12 mo
  • Royal Cassia+29 mo

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 29 months, for Royal Cassia (P52100026939).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology