Meghaswana Constructions

Company or firm · 6 projects · 6 MahaRERA registrations

6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
25 KaratP52100006816Talegaon Dabhade (M Cl)2017Certificate Signed30 Dec 201830 Dec 2018On date
25 Karat MoonstoneP52100024150Talegaon Dabhade (M Cl)2020Certificate Signed30 Jun 202330 Jun 2023On date
25 Karat AmethystP52100024166Talegaon Dabhade (M Cl)2020Certificate Signed30 Jun 202330 Jun 2023On date
25 Karat SapphireP52100025520Talegaon Dabhade (R)2020Certificate Signed30 Dec 202230 Dec 2022On date
Bhakti MalharP52100077845Talegaon Dabhade (M Cl)2024Certificate Signed31 Dec 202731 Dec 2027On date
Bhakti LegacyP52100079660Talegaon Dabhade (M Cl)2025Certificate Signed31 Mar 202931 Jul 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 25 KaratOn date
  • 25 Karat MoonstoneOn date
  • 25 Karat AmethystOn date
  • 25 Karat SapphireOn date
  • Bhakti MalharOn date
  • Bhakti Legacy+4 mo

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Bhakti Legacy (P52100079660).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology