Meenamani Ganga Builders Llp

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+9 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ganga Fernhill Phase IP52100000838Undri2017Not reported30 Dec 202130 Jun 2023+18 months
Ganga Fernhill phase 02P52100022705Undri2019Not reported30 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ganga Fernhill Phase I+18 mo
  • Ganga Fernhill phase 02On date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Ganga Fernhill Phase I (P52100000838).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology