Mayfair Enterprises

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+14 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Om SaiP99000013687Khairepada2017Not reported28 Jul 201927 Jan 2021+18 months
Sai Savali Building A1P99000026399Khairepada2020Not reported15 Dec 202315 Oct 2024+10 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Om Sai+18 mo
  • Sai Savali Building A1+10 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Om Sai (P99000013687).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology