Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mauli Nagar 5P50500026863Beltarodi2020Not reported30 Jun 2022—On date
Mauli Nagar 4P50500027211Nagpur (M Corp.)2020Not reported30 Jun 2022—On date
Mauli Nagar 8P50500030464Ghogali2021Not reported31 Dec 2022—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mauli Nagar 5On date
  • Mauli Nagar 4On date
  • Mauli Nagar 8On date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology