Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gurumauli ApartmentP52800004757Karle (Ct)2017Not reported31 Dec 2019—On date
Swami Prasad ApartmentP52800024369Malgund2020Not reported15 Dec 2024—On date
Shree Samarth SangamP52800026751Nachane (Ct)2020Not reported30 Nov 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gurumauli ApartmentOn date
  • Swami Prasad ApartmentOn date
  • Shree Samarth SangamOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology