Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Matrix ImperialP51700054466Navi Mumbai (M Corp.)2024Not reported31 Dec 2028—On date
Matrix AspireP51700079675Navi Mumbai (M Corp.)2025Certificate Signed30 Jun 203130 Oct 2031+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Matrix ImperialOn date
  • Matrix Aspire+4 mo

Track record notes

  • Longest extension on record: 4 months, for Matrix Aspire (P51700079675).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology