Matoshri Buildcon

Company or firm · 5 projects · 5 MahaRERA registrations · 2 reported completed

5Projects5 RERA registrations
2Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ekavira ApartmentP51600016085Nashik2018Certificate Signed30 Dec 202230 Dec 2022On date
Mahalaxmi TowersP51600018172Nashik2018Completed30 Dec 2023—On date
Mahalaxmi SankulP51600021627Nashik2019Completed30 Mar 2024—On date
Dwarkadhish ApartmentP51600024309Nashik2020Certificate Signed30 Dec 202330 Dec 2023On date
Nalini Vijay ApartmentP51600030761Nashik2021Certificate Signed31 Dec 202631 Dec 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ekavira ApartmentOn date
  • Mahalaxmi TowersOn date
  • Mahalaxmi SankulOn date
  • Dwarkadhish ApartmentOn date
  • Nalini Vijay ApartmentOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology