Mathuresh Infrapro Private Ltd
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+27 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| MonopoliP51900049902 | Ward Fsouth | 2023 | Certificate Signed | 27 Sep 2027 | 31 Dec 2029 | +27 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 27 months, for Monopoli (P51900049902).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology