Marvel Landmarks Pvt Ltd
Company or firm · 5 projects · 6 MahaRERA registrations
5Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
60%Kept RERA date3 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Marvel Ganga Sangria A,B,C BuildingP52100001815 | Mohammadwadi | 2017 | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Marvel Isola J BuildingP52100001843 | Mohammadwadi | 2017 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Marvel Ganga SangriaP52100002064 | Mohammadwadi | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Marvel Ganga SangriaP52100002371 | Mohammadwadi | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Marvel Ganga Sangria K,L,M BuildingP52100002514 | Mohammadwadi | 2017 | Certificate Signed | 30 Jun 2019 | 29 Dec 2020 | +18 months |
| Marvel Zephyr Building UP52100010976 | Kharadi | 2017 | Certificate Signed | 31 Jul 2018 | 31 Jul 2018 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Marvel Ganga Sangria K,L,M Building (P52100002514).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:MARVEL ISOLA J BUILDING (Regulatory Case No. 200 OF 2024) dated 30 May 2024. · Marvel Isola J Building · P52100001843 · 30 May 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology