Mark Bulidcon

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+23 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Silver TreasureP52100013384Wadagaon (Ct)2017Certificate Signed30 Jun 202130 Dec 2022+18 months
Silver TreasureP52100013392Wadagaon (Ct)2017Certificate Signed30 Dec 202331 Mar 2026+27 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Silver Treasure+18 mo
  • Silver Treasure+27 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 27 months, for Silver Treasure (P52100013392).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology