Marigold Reality
Company or firm · 1 project · 2 MahaRERA registrations · 1 reported completed
1Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sumeru VedantaP50300016756 | Amravati (M Corp.) | 2018 | Completed | 28 Feb 2021 | 30 Apr 2022 | +14 months |
| Sumeru VedantaP50300030777 | Amravati (M Corp.) | 2021 | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 14 months, for Sumeru Vedanta (P50300016756).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology