5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Marathon Nextown EmeraldP51700000686Thane (M Corp.)2017Certificate Signed30 Jun 201929 Dec 2020+18 months
Marathon Nextown CoralP51700000952Thane (M Corp.)2017Certificate Signed31 Dec 202230 Jun 2023+6 months
Marathon Nextown SapphireP51700001265Thane (M Corp.)2017Certificate Signed30 Dec 202129 Jun 2024+30 months
Marathon Nextown RubyP51700021189Thane2019Certificate Signed31 Dec 202630 Apr 2027+4 months
Marathon Nextown JasperP51700049449Thane (M Corp.)2023Certificate Signed31 Dec 202730 Dec 2028+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Marathon Nextown Emerald+18 mo
  • Marathon Nextown Coral+6 mo
  • Marathon Nextown Sapphire+30 mo
  • Marathon Nextown Ruby+4 mo
  • Marathon Nextown Jasper+12 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Marathon Nextown Sapphire (P51700001265).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology