Marathon EnerGen
Company or firm · 5 projects · 5 MahaRERA registrations
Also appears as MARATHON ENER-GEN
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Marathon Nextown EmeraldP51700000686 | Thane (M Corp.) | 2017 | Certificate Signed | 30 Jun 2019 | 29 Dec 2020 | +18 months |
| Marathon Nextown CoralP51700000952 | Thane (M Corp.) | 2017 | Certificate Signed | 31 Dec 2022 | 30 Jun 2023 | +6 months |
| Marathon Nextown SapphireP51700001265 | Thane (M Corp.) | 2017 | Certificate Signed | 30 Dec 2021 | 29 Jun 2024 | +30 months |
| Marathon Nextown RubyP51700021189 | Thane | 2019 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Marathon Nextown JasperP51700049449 | Thane (M Corp.) | 2023 | Certificate Signed | 31 Dec 2027 | 30 Dec 2028 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 30 months, for Marathon Nextown Sapphire (P51700001265).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology