Maple Estates
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Aapla Ghar Chakan Phase IIP52100004796 | Nanekarwadi (Ct) | 2017 | Not reported | 30 Dec 2022 | — | On date |
| Aapla Ghar Chakan Phase I Amentiy A BldgP52100005203 | Nanekarwadi (Ct) | 2017 | Not reported | 30 Jun 2021 | 30 Dec 2022 | +18 months |
| Aapla Ghar Chakan Phase II Amenity Bldg AP52100008123 | Nanekarwadi (Ct) | 2017 | Not reported | 30 Dec 2022 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Aapla Ghar Chakan Phase I Amentiy A Bldg (P52100005203).
Regulatory cases across projects
- DeregisteredDeregistered: Aapla Ghar Chakan Phase II Amenity Bldg A · Aapla Ghar Chakan Phase II Amenity Bldg A · P52100008123
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology