Maple City Developers
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Aapla Ghar Ranjangaon Phase IIP52100007009 | Ranjangaon Ganpati | 2017 | Not reported | 30 Dec 2022 | 31 Dec 2026 | +48 months |
| Aapla Ghar Sanaswadi Phase III 1P52100007230 | Dingrajwadi | 2017 | Not reported | 30 Dec 2023 | — | On date |
| Aapla Ghar Talegaon Dhamdhere Phase IP52100008882 | Talegaon Dhamdhere | 2017 | Not reported | 30 Dec 2021 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 48 months, for Aapla Ghar Ranjangaon Phase II (P52100007009).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology