Mantri Brothers
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+60 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mantri Business PlazaP51800015633 | Kurla | 2018 | Certificate Signed | 30 Dec 2021 | 31 Dec 2026 | +60 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 60 months, for Mantri Business Plaza (P51800015633).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: MANTRI BUSINESS PLAZA (Regulatory Case No. 355 OF 2025) dated 22 July, 2025. · Mantri Business Plaza · P51800015633 · 22 Jul 2025
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology