Mantra Island Homes Talegaon Llp
Company or firm · 5 projects · 5 MahaRERA registrations
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date20%1 of 5 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 4 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mantra City 360 Phase04P52100001457 | Talegaon Dabhade (M Cl) | 2017 | Not reported | 31 Oct 2019 | 1 Jul 2024 | +57 months |
| Mantra City 360 Phase02P52100001834 | Talegaon Dabhade (M Cl) | 2017 | Not reported | 31 Jan 2020 | 30 Jan 2022 | +24 months |
| Mantra City 360 Phase01P52100001846 | Talegaon Dabhade (M Cl) | 2017 | Not reported | 31 Oct 2019 | 30 Oct 2021 | +24 months |
| Mantra City 360 Phase03P52100002880 | Talegaon Dabhade (M Cl) | 2017 | Not reported | 31 Oct 2019 | 30 Oct 2021 | +24 months |
| Mantra City 360 Phase 06P52100016953 | Talegaon Dabhade (M Cl) | 2018 | Not reported | 30 Dec 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 5 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 57 months, for Mantra City 360 Phase04 (P52100001457).
Regulatory cases across projects
- DeregisteredDeregistered: MANTRA CITY 360 PHASE 06 · Mantra City 360 Phase 06 · P52100016953
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology