Manthan Development Corporation

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Manthan EmbassyP51800004366Kurla2017Not reported31 Dec 2028—On date
Manthan PlazaP51800005360Kurla2017Not reported30 Dec 2027—On date
Manthan AcropolisP51800015626Kurla2018Not reported30 Dec 202231 Dec 2026+48 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Manthan EmbassyOn date
  • Manthan PlazaOn date
  • Manthan Acropolis+48 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Manthan Acropolis (P51800015626).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology