Mansh Builder And Developer
Company or firm · 3 projects · 5 MahaRERA registrations
3Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mansh AvenueP52000013017 | Kharghar | 2017 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Mansh HomesP52000024503 | Vadghar (Ct) | 2020 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Bhaveshwar CallistaP52000047923 | Kalamboli | 2022 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Bhaveshwar CallistaP52000047932 | Kalamboli | 2022 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Bhaveshwar CallistaP52000051002 | Kalamboli | 2023 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Bhaveshwar Callista (P52000047923).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology