Manoj Vasant Mahadik
Individual promoter · 5 projects · 5 MahaRERA registrations
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Siddhi Ganesh ParkP52900021035 | Kokisare | 2019 | Not reported | 30 May 2027 | — | On date |
| Shree ResidencyP52900025958 | Tarele | 2020 | Not reported | 30 Nov 2023 | — | On date |
| Morya ResidencyP52800026050 | Lanja (Ct) | 2020 | Not reported | 30 Jun 2026 | — | On date |
| Shree Mahalaxmi ResidencyP52900027974 | Anandnagar | 2021 | Not reported | 30 Jun 2026 | — | On date |
| Mahadik PlazaP52900055325 | Tarele | 2024 | Not reported | 31 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- DeregisteredDeregistered: SHREE MAHALAXMI RESIDENCY · Shree Mahalaxmi Residency · P52900027974
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology